PLAN IMPLEMENTATION
Tracking the Use of
Disposal Sites
In order to effectively implement and
periodically update the Dredged Material Management Plan, the
amount of material placed in each disposal site must be monitored.
Local jurisdictions shall require that dredging and disposal
permit applicant's report the location and amount of material
actually disposed of to CREST. Sponsors of on-going projects,
such as the Corps of Engineers maintenance dredging, shall periodically
report disposal volumes, sites and pre- and post-bathymetry of
estuarine in-water disposal sites to affected local jurisdictions
and to CREST, notwithstanding the reporting requirements of State
and Federal agencies. CREST will compile records of all dredged
material disposals in the estuary area in order to assist local
jurisdictions in plan implementation and update. CREST has accumulated
disposal site use history and will continue to track and update
this information. |