|
APPENDIX D
Agency Standard Removal/Fill
Permit Conditions
The following is a list of standard
conditions that may be added to removal/fill permits by the U.S.
Army Corps of Engineers and the Oregon Division of State Lands.
The list is provided for informat- ional purposes.
Division of State
Lands
a. General
i. Care shall be taken to prevent any petroleum products, chemicals,
or other deleterious materials from entering water.
b. Water Quality, Riparian,
Fish & Wildlife
ii. Work in the waterway shall be done so as to minimize turbidity
increases in the water that would degrade water quality and damage
aquatic life. Turbidity shall not exceed 10% above natural stream
turbidities, except as allowed by OAR 340-41.
iii. Turbid waste waters from the project shall be provided adequate
settling time.
iv. Waste materials and spoils shall be placed above the bankline behind
previously constructed berms and not in any unauthorized wetland
areas.
v. Waste water from hydraulic dredging operation shall comply with
appropriate water quality standards.
vi. Rock riprapping and placement of bulkheads shall be done between
March 1 and January 1 and shall be constructed in a manner that
does not appreciably increase the upland surface area. Only clean,
durable riprap should be used, and the completed revetment shall
have a slope no steeper than 1 1/2:1.
vii. The disturbed areas above the riprap shall be revegetated
and landscaped
to prevent soil erosion.
viii. The Division of State Lands retains the authority to temporarily
halt of modify the project in case of excessive turbidity of
damage to natural resources.
ix. Removal of existing woody vegetation shall be minimal.
c. In-water dredging
and disposal
x. Dredging in the permit area shall be conducted between November
1 and February 28.
xi. If a bucket dredge of any type, including but not limited
to grab
or clamshell, dipper, dragline or backhaul bucket is used, all
digging passes of the bucket shall be completed without any material,
once in the bucket, being returned to the wetted area except
as approved.
xii. If a hydraulic dredge is used, the dredge is to be operated with
the intake on or below the surface of the material being removed.
xiii. During hydraulic dredging, the return water discharge from the
disposal area must be over a weir structure that is designed
and operated so the water crest height over the weir does not
exceed three inches at maximum flows.
xiv. Levees and weirs should be designed to regulate disposal pond
water depth to an average of two feet whenever a discharge is
occurring.
xv. Material shall not be removed to a depth greater than depicted
on the permit drawing.
xvi. The maintenance dredge spoil site shall be limited to the minimum
area needed.
xvii. The maintenance dredge spoil site shall be replanted with after
disposal is completed.
xviii. A drag-line bucket dredge shall only be used adjacent
to the shoreline
or if debris precludes using a hydraulic dredge. A single pass
with the bucket shall be made each time from the point of dredging
to a bermed disposal area or a dump truck.
Army Corps of Engineers
a. General
i. All construction debris shall be disposed of in such a manner
that it cannot enter the waterway.
ii. Care shall be taken to prevent any petroleum products, chemicals,
or other deleterious materials from entering the waterway.
iii. Your use of the permitted activity must not interfere with
the publics
right to free navigation on all navigable waters of the United
States.
iv. You must advise this office in writing at least two weeks before
you start maintenance dredging activities under the authority
of this permit.
v. You must install and maintain, at your expense, any safety
lights and
signals prescribed by the U.S. Coast Guard through regulations
or otherwise, on your authorized facilities.
vi. The Coast Guard must be notified by letter 14 days prior
to commencing
dredge operations.
vii. The method of dredging or disposal or the dredge or disposal locations
may not be changed without the prior written approval of the
District Engineer.
viii. You must have a copy of this permit available on the vessel used
for the authorized transportation and disposal of dredged material.
b. Water Quality, Riparian,
Fish & Wildlife
ix. Work in the waterway shall be done so as to minimize turbidity
increases in the water that tend to degrade water quality and
damage aquatic life.
x. All areas along the bank, disturbed or newly created by the construction
activity, shall be seeded, sodded, revegetated, or given some
other equivalent type of protection against subsequent erosion.
xi. When the District Engineer has been notified by a fishery agency
that a filling activity is adversely affecting fish or wildlife
resources or the harvest thereof, and when the District Engineer
subsequently directs remedial measures, the permittee shall comply
with such directions as may be received to suspend or modify
the activity, to the extent required to mitigate or eliminate
the adverse effect.
xii. When the District Engineer has been notified by the Department
of Environmental Quality that the dredging activity is adversely
affecting water quality, and the District Engineer subsequently
directs remedial measures, the permittee shall comply with directions
to suspend or modify the activity to mitigate or eliminate the
adverse effect.
c. In-water dredging
and disposal
xiii. All in-water work, including temporary fills, shall occur
within the Oregon Department of Fish and Wildlife preferred work
period, which is between November 1 and February 28 for the lower
Columbia River.
xiv. Material shall not be removed to a depth greater than -40 feet
Mean Lower Low Water.
xv. The discharge point shall be subsurface (-5 feet MLLW) and directed
downstream. The discharge pipe shall be marked according to Coast
Guard Standards.
xvi. Discharge may commence disposal operations when the bottom
water is ebbing or approximately one-hour after the beginning
of the start of surface ebb.
xvii. The hydraulic dredge is to be operated with the intake
on or below
the surface of the material being removed.
xviii. Back washing of the hydraulic dredge intake line shall
be held
to an absolute minimum. When backwashing is necessary, the intake
shall be raised no more than 3 feet above the river bottom.
xix. The discharge pipe shall be sunk when not in use to a depth sufficient
to insure it does not impede or create a hazard to navigation
xx. If a bucket dredge of any type, including but not limited
to grab
or clamshell, dipper, dragline, or backhaul bucket, is used,
all digging passes of the bucket shall be completed without any
material, once in the bucket, being returned to the wetted areas.
d. testing
xxi. Contact the Portland District Corps Regulatory Office to
evaluate the need for sediment testing. The notification shall
be a minimum of 4 months before the desired start date. The decision
regarding testing requirements will be based on the protocol
established in the "Dredged Material Evaluation Framework
- Lower Columbia River Management Area, November 1998." |